Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
From mid‑August through the end of September 2021 the interconnector carried progressively larger test transmissions — up to the full 1,400 MW design when conditions allowed — to validate market coupling, operational procedures and physical performance under near‑normal operating conditions ahead of the formal trial operation period.