Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Installation of submarine power cables at the North Hoyle Offshore Wind Farm was completed by December 2003, with export cable works finishing in October 2003 and intra-array cabling concluded in December as part of the overall construction campaign.