Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
The NorNed HVDC interconnector transmitted its first commercial power on 6 May 2008, marking the initial electricity transfer between the Norwegian and Dutch grids following the start of commercial operation of the 580 km, 700 MW ±450 kV subsea cable link.