Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
Commercial operation of the NorNed high‑voltage direct current submarine cable began on 5 May 2008 with a capacity auction, bringing the 580 km, 700 MW ±450 kV interconnector between Feda (Norway) and Eemshaven (Netherlands) into full market-based service.