Project advancing - milestone achieved
High Impact
Major milestone or critical setback
RWE took the Final Investment Decision for the 1.6 GW Nordseecluster offshore wind project, including the 660 MW Nordseecluster A phase, confirming full investment and enabling construction to proceed. The press release states that manufacturing of key components for Nordseecluster A had already started, with offshore construction scheduled to begin in 2025 and all 44 turbines to be connected to the grid by early 2027.