Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
DELAYED +0mo (May 2026): Latest RWE update (14 Apr 2026) says Nordseecluster A will be “fully operational from 2027” and separately says “After full commissioning at the beginning of 2027”. The current projection (2027-03-31) implies Q1 2027; aligning to the more specific ‘beginning of 2027’ commissioning language and keeping Q1 2027 as the appropriate precision anchor (rather than later in 2027). --- RWE states that Nordseecluster A, the 660 MW first phase of the 1.6 GW Nordseecluster offshore wind project around 50 km north of Juist, is planned to reach full commissioning and be fully operational in early 2027, after all 44 turbines are installed and connected to the grid. This timing is reiterated across RWE communications, which describe Nordseecluster A as being commissioned or fully operational from the beginning of 2027.