Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
On 27 May 2024, RWE stated that Hellenic Cables had been selected as cable manufacturer for its Nordseecluster offshore wind project, which includes the 660 MW Nordseecluster A phase. Hellenic Cables is to supply the inter-array cables connecting the 44 turbines of Nordseecluster A as well as high‑voltage grid connection cables for the wider 1.6 GW cluster.