Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Inter-array cable installation for Nordseecluster A started in early 2026: RWE stated in November 2025 that about 70 kilometres of internal cabling would be laid at the beginning of 2026, and by April 2026 reported that cable‑laying within the wind farm was underway. The campaign will connect the 44 turbines and two offshore substations of the 660 MW first phase prior to full commissioning in 2027.