Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Turbine installation at the Nordsee One offshore wind farm was completed on 22 September 2017, when the 54th and final Senvion 6.2M126 wind turbine was installed at the site approximately 40 km north of Juist Island. This marked the end of the offshore turbine installation campaign for the 332 MW project. Subsequent updates confirmed that all 54 turbines were feeding power into the grid from September 2017, enabling full commissioning and transition into commercial operation later that year.