Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
In 2015, Nordsee One GmbH reached a key construction milestone on the Nordsee One offshore wind farm with the successful installation of the first foundation. This marked the start of the foundation installation campaign for the 332 MW project located approximately 45 km off the German coast in water depths of 26 to 29 metres. The chronology on the company’s website records this “First Foundation successfully installed” event in 2015, indicating that offshore installation of the wind turbine foundations had commenced in the Nordsee One permit area, which is planned for 54 turbines. This initial installation signalled the transition from development and financing activities into the main offshore construction phase for the project.