On 7 June 2016, Nordsee One GmbH announced that the installation contractor had started laying the first inter-array cable within the Nordsee One construction area. The 54 turbines are to be connected to the offshore substation via ten strings of submarine cables with a total length of about 70 km. The press release notes that all 54 turbine foundations and the substation foundation were already installed, and that the inter-array cables would be laid and then buried in the seabed by specialised cable-laying vessels, with completion expected in autumn 2016.