In the 2024 German offshore wind tenders, the centrally auctioned site N-11.2 with a planned capacity of 1.5 GW in the North Sea was awarded via a dynamic zero‑cent‑bid auction. Nine bidders participated and the successful bidder secured the site by offering just under €1.1 million per megawatt, establishing the lease rights for developing this area.