Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
TotalEnergies targets commercial operations for the 1.5 GW NordSee Energies 2 (NSE2) offshore wind farm on N-11.2 in 2031, in unified line with its Nordsee Energies Hub schedule (NSE1 FID 2027, NSE2 FID 2028, construction 2029 for both, commissioning 2031). The NSE2 COD is calendar-locked alongside NSE1 despite a one-year-later FID, suggesting a compressed construction window or that the 2031 date is the hub-level commissioning target with NSE2 potentially slipping behind. Source: TotalEnergies' 20 November 2025 permit-submission communications via offshorewind.biz.