Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
DELAYED +2mo (May 2026): Vattenfall’s full-FID press release (13 Jan 2026) states monopile installation for Nordlicht I is scheduled to start in Q3 2026 (not specifically July 2026). Shifting to quarter-end to match the stated schedule precision. --- Vattenfall plans to start the offshore foundation installation campaign for the 980 MW Nordlicht I wind farm in July 2026, beginning with the placement of monopile foundations and transition pieces as the first major construction phase at the site north of Borkum in the German North Sea.