Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
The onshore substation at Innhausen, north of Wilhelmshaven, which serves as the grid connection point for the Nordergründe offshore project, was expanded around 2013 to accommodate the 155 kV export link, enabling the power to be transformed to 220 kV and fed into the 220 kV transmission network after the 4 km land cable from the shore was laid starting in autumn 2012.