Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
TenneT completed installation of the Nordergründe export cable by the summer of 2016, finishing the laying of the 32km, 155kV AC connection comprising approximately 28km of subsea cable and 4km of onshore cable between the wind farm area and the Inhausen substation. From that point, the seaward end of the cable in the wind farm area was in place and awaiting connection into the offshore substation platform.