On 7 April 2022, a preliminary electrical design report for Nora Energia 1 prepared for Nora Ventu detailed the selection of the wind farm area between Sant’Antioco and Santa Margherita di Pula in the Sardinian Channel, explaining that the site choice was based on mapping wind resource potential, distance from shore, water depths of roughly 150–550 m, seabed characteristics, potential connection nodes on Terna’s national transmission network, and the need to minimise environmental and other spatial conflicts.