Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
OKEA’s Q2 2025 quarterly report states that protection of the installed power cable from shore to Draugen was completed during the quarter, and the Q3 2025 quarterly report further notes that all subsea power cable activities for the Draugen Power from Shore project were successfully completed. Together these indicate that installation and protection of the subsea power cable from Straum onshore to the Draugen platform were completed by the end of Q3 2025.