Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
NeuConnect plans to carry out testing and commissioning of the 1.4 GW GB–Germany interconnector between 2025 and 2027, following ongoing offshore cabling and converter station installation works. These system tests will verify the performance and reliability of the HVDC link before the project enters operation, currently targeted for 2028.