Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
By late November 2024 NeuConnect had completed the first phase of its cabling works on land and in UK waters, installing a total of 56 km of HVDC cable. This stage included subsea cables laid and buried beneath the seabed by Prysmian’s Cable Enterprise vessel as well as associated onshore sections, marking a significant early milestone in the 725 km cabling programme.