Positive
Project advancing - milestone achieved
Low Impact
Minor progress or informational
A pre-lay trenching campaign for Neart na Gaoithe’s inter-array cable routes took place between August and September 2021, using mechanical cutting and jetting trials in areas of harder sediment and including a 300‑metre trial cable burial and removal, with pre‑, interim, and post‑surveys to inform and de‑risk the full inter-array cable installation campaign.