The Neart na Gaoithe Offshore Decommissioning Programme indicates that once decommissioning starts around 25 years after final commissioning, full decommissioning of the project is expected to take approximately 12 months, with offshore decommissioning and onshore dismantling of recovered infrastructure running in parallel. On this basis, completion of decommissioning is planned to occur roughly one year after the commencement of decommissioning activities.