Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Inter-array cable installation at Neart na Gaoithe was completed on 7 January 2024 when DEME’s vessel Viking Neptun finished laying all inter-array cables, after installation activity that had run from April 2023; subsequent burial by Living Stone and associated works continued into early 2024 to finalise the inter-array cable system.