Two horizontal directional drills were completed beneath the Thorntonloch Beach landfall in early 2021, with ducts installed to allow the Neart na Gaoithe offshore export cables to be pulled ashore and joined to the onshore export cables leading towards the Crystal Rig onshore substation, completing the key landfall civil works for the OFTO export route.