The Neart na Gaoithe transmission asset schedule shows that installation of the two offshore 220 kV export cables between the NnG offshore substations and the Thorntonloch Beach landfall was carried out from June to July 2021, completing the offshore export cable installation scope that will form part of the Neart na Gaoithe OFTO.