Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Offshore construction start projected for 2035 using the COD-minus-2-years heuristic anchored to the NOR-16-2 (50Hertz) grid system IBN 2037 per NEP 2025 Tabelle 21 / Projektsteckbrief. Subject to future BSH FEP formalisation of post-2034 site-pairings, BNetzA auction, FID, supplier selection and supply-chain status. Date precision is year-level given the long lead time.