Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Offshore construction start projected for 2038 using the COD-minus-2-years heuristic anchored to the LanWin8 (NOR-13-2, 50Hertz) grid system IBN 2040 per NEP 2025 Tabelle 21 / Projektsteckbrief. Paired with N-13.3 on the LanWin8 connection. Subject to future BSH FEP formalisation, BNetzA auction, FID, supplier selection and supply-chain status. Date precision is year-level given the long lead time.