Negative
Setback or risk materialised
High Impact
Major milestone or critical setback
German federal cabinet approved a drafting aid (Formulierungshilfe) suspending all 2026 offshore wind auctions, citing converter platform fabrication delays. BSH amended FEP 2025 on 30 January 2026, shifting six sites including N-10.2 into the 2027 auction window. Anticipated commissioning slips to ~2032 Q3 per the amended FEP Tabelle 6/7.