Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Muir Mhòr Offshore Wind Farm Ltd plans to commission up to two Offshore Electrical Platforms (OEPs) hosting HVAC equipment in 2030, before grid connection and first power in the same year. The project's Pre-Application Consultation schedule and OfTI Marine Licence application place offshore construction over 2029-2032 with first generation in 2030; commissioning the OEPs is a prerequisite for energising the export circuits via the planned 400 kV SSEN Netherton Hub onshore connection. Year precision reflects that the developer's filings provide a single year for grid connection and first power rather than a discrete OEP commissioning date.