Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
In planning documents for the Moyle Returns cable replacement, Moyle Interconnector Limited indicated that, subject to timely consents and manufacturing availability, commissioning of the new low-voltage return cables was expected with full delivery of the EPC contract before the end of 2017, restoring the Moyle Interconnector to full 500MW operational capability.