Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Onshore cable construction for the Moyle Return Cables Project transition joint commenced in both Scotland and Northern Ireland, including excavation of a small pit with a flat surface required for the jointing works. An outage on the existing cable was arranged over the weekend of 26–27 September 2015 to enable these onshore works, during which the pit was successfully excavated.