Negative
Setback or risk materialised
Medium Impact
Significant progress or notable issue
Network planning documents for Greenlink noted that from 10 November 2017 the Moyle Interconnector’s export capacity to Great Britain would be reduced to 80 MW, significantly below its 500 MW rating, pending completion of electricity network upgrades in Scotland, representing a binding grid‑imposed constraint on Moyle’s export capability rather than an asset failure.