Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
From 10 April 2002 the Moyle Interconnector moved from trial running into full commercial operation at its 500 MW design capacity, achieving 98.7% availability (99.2% on contracted capacity) with only a short planned outage during the July holiday period and an expected 400 MW capacity with design availability for the subsequent winter period.