Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Morven targets turbine installation in 2029, between foundation deployment in 2028 and first power in 2030 per the developer's working programme. As a 2.9 GW fixed-bottom offshore wind farm with up to around 200 turbines of 14-18 MW deployed across Morven North and Morven South arrays, turbine installation campaign typically spans 12-18 months and follows foundation pre-installation by 6-12 months. Port of Leith is the selected marshalling port. Year precision reflects phase-level scheduling on the developer's website.