By July 2018, the Morocco–Portugal HVDC interconnection (MAPT) between the 400 kV Tavira substation in Portugal and the 400 kV Beni Harchan(e) substation in Morocco was being studied under Med‑TSO’s Mediterranean Master Plan, with the two governments supporting the project and having launched several technical and network studies on the possible 1,000 MW, ~265 km HVDC link. These Med‑TSO tasks included detailed network and security analyses to identify necessary internal grid reinforcements and to evaluate technologies and configurations for the interconnector, promoted by REN and ONEE.