Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
REN and ONEE are targeting full commissioning of the 1,000 MW Morocco–Portugal HVDC interconnector between Béni Harchane and Tavira in the early 2030s, with an indicative schedule of procurement starting around 2027, a four‑to‑five‑year construction period, and system energisation before 2032, implying the link would be in commercial service early in the next decade.