Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
By 28 January 2026, Morecambe Offshore Windfarm Ltd had secured an agreed grid connection date with National Grid for the 480 MW Morecambe offshore wind farm, confirming that a grid connection agreement is in place to export power from the project into the UK transmission system.