Moray Offshore Windfarm (West) Limited issued a Notice to Mariners stating that pre-lay grapnel and pre-lay survey works, along with associated ROV route surveys, would be carried out from the vessels Seaway Aimery and Olympic Orion at the Moray West site as part of the array cable installation campaign starting mid-March 2024 and lasting around three months, to clear and survey cable routes prior to laying subsea power cables.