Neutral
Informational - no clear directional impact
Low Impact
Minor progress or informational
In a 26 November 2024 installation insight, Sea Impact reported that Moray West had completed its offshore construction phase in 415 days, noting that foundation installation was completed in 239 days and turbine installation in 215 days, using a phased approach with vessels including Boskalis’ Bokalift 2, DEME’s Orion 1 and Apollo for monopiles and transition pieces, Seaway7’s Seaway Aimery for inter-array cables, and Cadeler’s Wind Orca for turbine installation.