Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Offshore construction for the Moray West Offshore Transmission Infrastructure (OfTI), including installation of the offshore export cables and associated works in the OfTI corridor, was planned to commence in December 2022 and take approximately two years to complete, according to the project’s Export Cable Plan.