Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
On 9 December 2021, Moray Offshore Windfarm (West) Limited announced that it had selected Nexans to supply the onshore and offshore export cable system for the Moray West project, including 220 kV HVAC subsea export cables from the two offshore substation platforms to the onshore substation at Whitehillock and buried 400 kV cables connecting Whitehillock to the National Grid transmission system at Blackhillock near Keith. The turnkey contract covers design, manufacture, installation and protection of approximately 100 km of subsea and 170 km of land cables, providing the main transmission link that will later form the Moray West OFTO assets.