Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Wind turbine installation at Moray East started in mid-January 2021, when the jack-up vessel Bold Tern erected the first of 100 Vestas (MHI Vestas) 9.5 MW turbines at the offshore site some 22 kilometres off the Aberdeenshire coast, initiating the project’s main turbine installation campaign.