Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
DEME Offshore completed foundation installation at the 950 MW Moray East Offshore Wind Farm on 26 December 2020, safely installing the final jacket foundation as part of its EPCI scope for 100 wind turbine foundations and three offshore substation platform foundations despite COVID-19-related challenges.