Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
By 6 April 2021, all inter-array cables at the Moray East offshore wind farm had been laid by CLV Living Stone, with burial, termination, and testing activities continuing to finalise the internal electrical network connecting the 100 turbines to the offshore transformer modules.