Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
By mid-October 2020, all three export cables for the 950 MW Moray East offshore wind farm had been laid and pulled in by the cable-laying vessel NKT Victoria, completing the offshore export cable installation between the project’s offshore transformer modules and the onshore substation.