In February 2024, Mona Offshore Wind Limited submitted a Development Consent Order application to the Planning Inspectorate for the Mona Offshore Wind Project. The application covered the offshore wind farm generating station, up to four offshore export cable circuits at up to 275 kV from the array area to landfall at Llanddulas on the North Wales coast, onshore export cables, a new onshore HVAC substation, and 400 kV grid connection cables to the existing Bodelwyddan National Grid substation. The application was accepted for examination in March 2024.