Turnkey BoP scope included the internal array grid (33 kV inner array cables; total inner array length stated by DEME as 83 km).
GeoSea (DEME Group) acted as general/turnkey balance-of-plant contractor for the Merkur Offshore wind farm. Its scope included engineering, construction and installation of the foundations, the offshore substation and the internal array grid, and it also included offshore transport/installation activities for the wind turbine generators.