By early July 2013, VSMC had completed inter-array cabling for the Meerwind Süd|Ost offshore wind farm, installing the final cable and successfully executing the last pull-in. In total, the contractor achieved three load-outs, laid 88 inter-array cables and completed 176 pull-ins on time and without recordable incidents, finalising the infield cable installation for the 80‑turbine, 288MW project in the German Bight.