MarramWind targets turbine installation in 2032 as part of the phased offshore construction programme that commences in 2030 per the December 2025 EIA Chapter 4. For a 3 GW floating offshore wind farm with 126-225 turbines using tow-to-port hook-up onto previously deployed floating substructures, turbine installation typically follows foundation/mooring pre-installation by 12-24 months and precedes first power by 6-12 months, placing turbine installation start in 2032 between 2030 foundation deployment and first power around 2033. Year precision reflects phase-level scheduling in the developer's EIA.