Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Following completion of the subsea repair works in late 2022, Enemalta and Nexans successfully restored the Malta–Sicily interconnector to operational status, with testing and jointing works enabling the cable to be re‑energised and reintegrated into Malta’s power mix after the storm‑related damage.